How many working days in year 2012?
Here is the detail of the calculation:
Because 2012 is a leap year, it has 366 days.
Let's remove 52 saturdays and 53 sundays. It remains 261 days.
Now, let's remove 10 public holidays that do not fall during a weekend and we obtain 251 working days in 2012.
Here is the list of these 10 public holidays:
1. Día de los Santos Reyes : Friday, 6 January, 2012
2. Día de Juan Pablo Duarte : Thursday, 26 January, 2012
3. Día de la Independencia Nacional : Monday, 27 February, 2012
4. Viernes Santo : Friday, 6 April, 2012
5. Día del Trabajo : Monday, 30 April, 2012
6. Corpus Christi : Thursday, 7 June, 2012
7. Día de la Restauración de la República : Thursday, 16 August, 2012
8. Nuestra Señora de las Mercedes : Monday, 24 September, 2012
9. Día de la Constitución : Monday, 5 November, 2012
10. Navidad : Tuesday, 25 December, 2012
And here are the 2 public holidays falling on a weekend:
1. Año Nuevo : Sunday, 1 January, 2012
2. Día de Nuestra Señora de la Altagracia : Saturday, 21 January, 2012